- Assemble PROPOSED MW DISH.
- Assemble ODU.
- Attach ODU to the PROPOSED MW DISH.
- Assemble the PROPOSED PIPE MOUNT.
- Relocate the EXISTING MW DISH, EXISTING MW ODU, and EXISTING PIPE MOUNT.
- Repeat steps 1-5 on the second site and the path to the EXISTING EQUIPMENT to the previous specifications.
- Move the proposed technology and equipment into place: PROPOSED MW DISH, ODU, and ODU onto the MW DISH.
- Run the cabling and snap it into place.
- Ground cables and ODU as requested.
- Plug cables into specific ports on ODU and in the cabinet.
- Repeat steps 7-10 on the second site.
- Path new technologies to specifications found on the link-specific data sheet.
- Decommission old technology and cabling from both sites.